Building the Bridge 7

Created: June 2, 2010

When selecting construction materials, we chose the lightweight tempered service board. It was affordable, pliable, and we thought superior to the more expensive plywood. Unfortunately, as seen in the picture top left, the seams were visible when taking photos. They would certainly show up in our film, so it was time to consider our options! We briefly considered molding like we used on the helm station, but chose instead to try using duct tape and painting over it.

It didn't work.

The duct tape reacted badly to the paint, and simply fell off. I was disappointed; duct tape had helped my father-in-law's foundering boat off the coast of Miami, and yet it just couldn't hold on to latext paint under the high humidity for more than a few hours.

Our second choice was sheet rock mud. (We tried bondo, but it proved too difficult to work with, possibly due to the rainy weather we've had for the past week--which may have been our issue with the duct tape.) We applied sheet rock tape and mudded over it. Then we sanded it to a smooth finish, and still could see light seeping through the seams. So with Ryan's help, we applied strips of Gorilla Tape across the sanded features along the seams.

View from the front.

You can see the seems on both stations.

It was felt that molding was not an option. It had proved expensive and very difficult when working on our helm station. Clearly we had to try other options...

BTW, the opening in the back is the "back door" to the captain's ready room.

Comm Station After Bondo

On Friday, I applied the sheet rock mud over the mud tape on order to seal the seams.

Security & Tactical Get Plastered

On Saturday, we saw that the seams still let light through, so we used Gorilla Tape to further cover the seams. Ryan (our middle child) held the ends while I carefully unrolled strips long enough.

BTW, the opening to the left is the mainviewer. You can see we open the tarp up when working during the day.

Securing the Gorilla Tape to the Corners Could Be a Sticky Situation

The Gorilla Tape worked quite well over the sanded sheet rock mud.

After Painting the Controls, We Decided to Caulk the Underside

On Sunday, I made the decision to caulk the areas underneath again to prevent any stray outside light from coming in through the seams.

Engineering and Environmental Stand Ready

Once painted, the results look pretty good. We applied a second coat on Monday, and may apply a third on Friday.  

The Color Scheme Should Be Striking

On Tuesday, we painted the sides of the upper deck, front step and platform in preparation for next week's installation of the carpeting.

The carpeting will be industrial gray carpeting that should stand up to our filming conditions for at least three years. Much to my dismay, it's going to be a lot cheaper to simply glue the carpeting down. But as long as we don't run into any snags (ha!), it should last us for some time.

 

The Partitions Leaning Against the Dummy Turbolift Entrance

On Wednesday, we painted the sides of the station partitions, and stood them where we intend to place them in order to get some measurements and an idea of how they'll look once installed.

Our engineering consultant (ahem, my wife) reviewed the plans and made a few corrections before approving them. We hope to build the dummy lift tomorrow.

Widening the Closet Door Was a lot of WORK

And lest I forget, this was last Thursday evening's project: the widening of the carport closet door to allow for us to construct our 'working' turbolift. The doors will open up onto a small turbolift set constructed in this area.

The construction schedule for the coming week:

Thursday: Construction and Installation of Dummy Turbolift and Partition Lighting
Friday: Installation of Set Lighting (over each station post, we'll be installing a spotlight); Construction and Installation of Front Partitions and Partition Lighting (along each side of the viewscreen)
Saturday: Construction and Installation of Mainviewer
Sunday: Design and Construction of Captain's Chair's arms and controls
Monday: Construction and Installation of Working Turbolift Doors, Partitions and Partition Lighting
Tuesday: Installation of Upper Deck Ballisters, Trim and Trim Lighting
Wednesday: Installation of Upper Deck Bannister

Assuming all that goes well (and it most certainly won't, but we can all dream, can't we?), we've got the following:

Installation and Construction of Captain's Ready Room access (the "back door") and side panels
Installation of Carpeting
Installation of Control Panels

And if we get enough donations:

Installation of Window Unit Air-Conditioner
Installation of Vinyl Enclosure for Carport

Sadly, funding is actually a major factor right now for all our plans. We literally could be ready to shoot in two weeks if we receive enough donations to cover the expenses associated with the set construction.

Every little bit helps, even $5 or $10 with which we can buy lumber and paint. $20 or $30 helps us purchase plywood. $50 or $60 allows us to purchase fixtures like the ballisters and bannisters. $100 can go to the cost of the carpeting. We estimate if 60 fans gave $25 each, we'd have the remainder of our construction costs covered and filming could start within the month.

So please keep us in mind. Help us make the Project: Potemkin film a reality! Click below to make a donation today!



Free counters provided by Vendio.

usspotemkin.gif (6515 bytes)

Click Above to Return to the Main Menu